If 48 men can do a piece of work in 25 hours, how much time will it take for 15 men to finish the
same task?
A. 75 hours
B. 60 hours
C. 80 hours
D. 85 hours
Understanding Work and Man-Hour Concepts
Work problems involving men and time are common in aptitude tests and real-life planning. They revolve around the concept of man-hours, which combines the number of workers and the time they work.
The Given Scenario:
- 48 men can complete a job in 25 hours.
- How long will 15 men take to do the same job?
Step-by-Step Calculation
Let’s calculate the total amount of work in man-hours:
Total Work = Number of Men × Time
= 48 men × 25 hours
= 1200 man-hours
Now, if 15 men are doing the same 1200 man-hours of work, we calculate the required time:
Time = Total Work / Number of Men
= 1200 / 15
= 80 hours
Final Answer:
- A. 75 hours – Incorrect
- B. 60 hours – Incorrect
- C. 80 hours – ✅ Correct Answer
- D. 85 hours – Incorrect
Key Takeaways
- Total work remains constant in such problems.
- Work is calculated using the formula: Work = Men × Time.
- Fewer workers mean more time required, assuming constant efficiency.
Understanding this concept helps in planning labor for construction, event management, and project timelines in various industries.
13 Comments
Suman bhakar
April 6, 2025Done sir 👍
Akshay mahawar
April 7, 2025Done 👍
Ujjwal
April 15, 2025✔️✔️
Beena Meena
April 16, 2025Done
VIKRAM GAHLOT
April 16, 2025👍
Khushi yadav
April 17, 2025Done
Nisha Meena
April 17, 2025Best explanation
Mosam gurjar
April 17, 2025Done 👍
Vishakha pareek
April 17, 2025Done👍
Priyam choudhary
April 20, 2025Complete ✅
pallavi gautam
April 21, 2025done
Abhishek
April 24, 2025Done ✅
yogesh sharma
May 3, 2025Done sir ji