11. 8 professionals can paint a house in 12 days. However, it takes 12 amateurs 16 days to paint the same house. 16 professional painters started painting the house. After 3 days, 10 of them were replaced by 4 amateurs. Now how many days will they take to complete the remaining painting? a. 8 days b. 10 days c. 12 days d. 6 days

11. 8 professionals can paint a house in 12 days. However, it takes 12 amateurs 16 days
to paint the same house. 16 professional painters started painting the house. After 3
days, 10 of them were replaced by 4 amateurs. Now how many days will they take to
complete the remaining painting?
a. 8 days
b. 10 days
c. 12 days
d. 6 days

They will take 8 more days to complete the remaining painting, so the correct answer is (a) 8 days.

Time and Work Problem: Professionals and Amateurs

This question is a classic time and work problem with professionals and amateurs that tests your ability to compare individual work rates and handle changes in workforce over time. Such problems are common in competitive exams and require a clear understanding of how to convert days and workers into a single rate-based framework.

Step-by-Step Solution

1. Find individual work rates

Let the whole work (painting the house) be 1 unit of work.

  • 8 professionals can paint the house in 12 days.
  • Combined rate of 8 professionals = 1/12 work per day.
  • So rate of 1 professional = 1/12 ÷ 8 = 1/96 work per day
  • 12 amateurs can paint the house in 16 days.
  • Combined rate of 12 amateurs = 1/16 work per day.
  • So rate of 1 amateur = 1/16 ÷ 12 = 1/192 work per day

Summary:

  • 1 professional = 1/96 work per day
  • 1 amateur = 1/192 work per day

2. Work done in the first 3 days

16 professionals start the work.

  • Rate of 16 professionals = 16 × 1/96 = 16/96 = 1/6 work per day
  • Work done in 3 days = 3 × 1/6 = 3/6 = 1/2

So, half of the house is already painted in 3 days.

Remaining work = 1 – 1/2 = 1/2

3. New team’s daily work rate

After 3 days, 10 professionals are replaced by 4 amateurs.

  • Initially: 16 professionals
  • After change: Professionals left = 16 – 10 = 6 professionals
  • Amateurs added = 4 amateurs

Now compute their combined rate:

  • Rate of 6 professionals = 6 × 1/96 = 6/96 = 1/16
  • Rate of 4 amateurs = 4 × 1/192 = 4/192 = 1/48
  • Total rate of new team = 1/16 + 1/48 = 3/48 + 1/48 = 4/48 = 1/12 work per day

So the new team (6 professionals + 4 amateurs) can paint 1/12 of the house per day.

4. Time to complete remaining work

  • Remaining work = 1/2
  • Daily rate of new team = 1/12
  • Time required = Work/Rate = (1/2) ÷ (1/12) = 1/2 × 12/1 = 6 days

So, it will take 6 days more to finish the remaining painting.

Total duration = 3 days (initial) + 6 days (after replacement) = 9 days, but the question asks only for the days needed to complete the remaining painting, which is 6 days.

Correct Answer

(d) 6 days

Explanation of All Options

Option (a) 8 days
This would arise if someone incorrectly calculates the combined rate of the new team or miscalculates the remaining work as less or more than half. It is a common trap when fractions are not simplified correctly.
Option (b) 10 days
This likely comes from ignoring the rate change and using an average or incorrect proportional method, such as assuming amateurs and professionals work at similar rates.
Option (c) 12 days
This matches the time 8 professionals take to paint a full house, so it reflects confusion between the original full-work time and the actual remaining half work with a mixed team.
Option (d) 6 days (Correct)
With a remaining work of 1/2 and a combined rate of 1/12 per day, time needed is 6 days, which is mathematically consistent with the given data.

Key Points for Exam Preparation

  • Always convert group work into individual work rates first.
  • Track work done and remaining work step by step when team composition changes.
  • Use the formula Time = Work/Rate consistently.
  • This structured approach helps in solving any time and work problem with professionals and amateurs efficiently in competitive exams.

 

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest Courses